Mexican President Andres Manuel Lopez Obrador has officially launched the $8 billion construction of a controversial oil refinery that experts say is likely to blow out in cost.

The huge project, inaugurated on Sunday, aims to boost Mexico’s struggling state oil company Pemex and provide economic stimulus to the country’s impoverished south.

“We will build it in three years at a cost of 150 billion pesos [$8 billion]. No doubt about it!” the leftwing president, better known as Amlo, said.

Experts, however, say the project will nearly double in cost and take some eight years to complete.

A group of foreign firms selected by the government were first granted the tender to build the Dos Bocas oil refinery in southeastern Tabasco state, where Amlo was born.

The tender was cancelled when the firms put forward completion dates and budget estimates greater than those demanded by the president.

The government then gave the project to the deeply indebted oil company Pemex.

Once completed, it would allow Pemex to process some 340,000 barrels of crude per day and deliver 170,000 barrels of petrol as well as 120,000 barrels of diesel.

Experts, however, doubt Pemex has the necessary experience to see the project through.

They also say it is a mistake to funnel resources into the new refinery instead of pushing the company to boost its dwindling production of petrol, which has fallen 50 per cent from its peak of 3.4 million barrels per day 15 years ago.

Pemex is more than $100 billion in debt and is losing some $1.9 billion each quarter. It has been criticised by credit agencies that have urged the company to invest more in exploration and production to avoid financial disaster.

Amlo says the refinery was needed to break Mexico’s dependence on foreign gasoline imports – some 70 per cent of what it uses – and would be a boost for growth for the south, which is the country’s poorest region.

“It is time for the southeast to work for the benefit of all – that’s where the natural resources are and where the petroleum is,” he said, adding the construction is an “act of justice” towards that part of the country.

It is thought the project will create some 100,000 jobs.

Pemex currently has six refineries which – because of a lack of investment – operate at less than one-third capacity.

Energy minister Rocio Nahle said refining oil was a “good business” and that if the refinery operated correctly, the investment could be made back in four to five years.

She added “all care has been taken” regarding the environment, following complaints no impact study had been carried out and mangroves would be destroyed in the construction area.