Logo of Phnom Penh Post newspaper Phnom Penh Post - Pursat solar farm in test phase

Pursat solar farm in test phase

Content image - Phnom Penh Post
More new solar power plants are expected to pop up in provinces such as Banteay Meanchey. Hin Pisei

Pursat solar farm in test phase

A 30MW solar power station located in Pursat province’s eastern Krakor district has been connected to the national grid as it enters its testing and commissioning phase.

The project is part of the government’s plan to boost the Kingdom’s clean-energy portfolio to 450MW by the end of 2022.

Keo Rottanak, the director-general of State-run electricity supplier Electricite du Cambodge (EdC), on Tuesday told online news outlet Fresh News that the solar power plant had been commissioned by the EdC to be connected to the national grid in Sna Ansa commune.

He was quoted as saying: “The 30MW generated by the project is part of the 200MW of solar energy set to be added to the energy mix in 2020-2022.

“The plan will accelerate the development of energy supply for next year, especially for the dry season, and is part of the commitments of the government and the EdC to increase the percentage of renewable and clean energy.”

Victor Jona, director-general of the Ministry of Mines and Energy’s General Department of Energy, told The Post on Tuesday that the project entered its testing and commissioning phase just after construction was completed “in mid-September”.

“The inclusion of new solar power in the national grid will give EdC even greater levels of excellence in the energy sector,” he said.

He added that with the efforts of the relevant authorities, he expects more new solar power plants to be put into operation in the future, mainly concentrated in provinces such as Kampong Chhnang, Pursat, Battambang and Banteay Meanchey.

The project will be equipped with Cheetah-brand photovoltaic panels provided by Shanghai-based New York Stock Exchange-listed Jinkosolar Holding Co Ltd.

JinkoSolar, the world’s largest producer of solar panels, said in January: “These particular panels have an average module efficiency of 20 per cent and are suitable for areas with high heat and humidity.”

From 2006 to the end of last year, investment in the electricity sector was worth a total of $6.1 billion, reflecting the increasing demand of the energy sector in recent years, the ministry reported.

Demand for electricity is growing at an average of 16-18 per cent annually, except from 2018 to last year, which saw a 25 per cent growth, it said.

The Kingdom can generate about 70-80 per cent of total electricity consumption, with the remainder met by imports from neighbouring countries, it added.

The Electricity Authority of Cambodia’s 2019 annual report says the Kingdom increased its electricity supply to 2,870.65MW last year, up from 2,650.26MW in 2018.

MOST VIEWED

  • 12th Cambodia int’l film festival to see return of Hollywood star

    Phnom Penh is set to come alive with the magic of cinema as the highly anticipated 12th Cambodia International Film Festival (CIFF) takes centre stage. Boasting an impressive line-up of 188 films from 23 countries, including captivating shorts, feature films, documentaries and animation, the festival promises an

  • Bareknuckle champion wants Kun Khmer fighter

    Dave Leduc, who is the current openweight Lethwei boxing champion in Myanmar, has announced that he will travel to Cambodia this year to challenge SEA Games gold medallist Prum Samnang any time that is convenient, after their planned match later this month in Slovakia was

  • Struggling Battambang artist dreams of staging full-scale gallery exhibition

    Leav Kimchhoth, a 55-year-old artist from Battambang province, is a familiar face to locals and tourists alike on the streets of the riverside in Phnom Penh. The one-armed painter and illustrator often hawks his work near the night market on weekends and public holidays. He

  • Fresh Covid warnings as Thai hospital fills

    A senior health official reminds the public to remain vigilant, as neighbouring countries experience an increase in Covid-19 cases, with the latest surge appearing to be a result of the Omicron XBB.1.5 sub-variant. Or Vandine, secretary of state and spokeswoman for the Ministry of Health,

  • 1.4 billion dollar Phnom Penh-Bavet expressway due in four years

    The Government, through the Ministry of Public Works and Transport, has officially signed a public-private partnership agreement with a private company for the construction of a Phnom Penh-Bavet Expressway project that will connect the capital to Svay Rieng province. The budget for the project is

  • New Law on Taxation comes into effect

    Cambodia has enacted the eagerly-awaited new Law on Taxation, which aims to improve the national tax regime’s compliance with present and future international standards and economic conditions; encourage accountability, effectiveness and transparency in the collection process; and promote investment in the Kingdom. King Norodom