Thailand set to hasten EV charging-station plan

Content image - Phnom Penh Post
Thailand plans to promote the use of electric vehicles (EVs) in four phases. THE NATION

Thailand set to hasten EV charging-station plan

Disruptive technology has affected Thailand’s electricity business and the automobile industry, causing the government and private sector to enhance performance in order to maintain the country’s competitiveness and production base to export cars in the region.

Minister of Energy Sontirat Sontijirawong said the ministry has prepared to present to the Cabinet the establishment of the national commission on electric vehicles (EV), with Deputy Prime Minister Somkid Jatusripitak as president.

He said if the plan were to be delayed, Thailand would lose the opportunity to be a production base of cars in the region.

The ministry recently directed the Energy Regulatory Commission to conduct a study on excess electricity reserves, or oversupply, in the country, which is around 30 per cent, to use as incentives such as the reduction of electricity bills in order to encourage investors to speed up the construction of electric charging stations for the public. The study will be reported by next month.

In addition, Sontirat ordered the Energy Policy and Planning Office and the Department of Energy Business to study amending the law to be consistent with the mapping of installation points for charging stations, which will give a clear picture of electric charging stations’ locations nationwide with specified distance radius of each station.

This will help avoid making redundant investments, diverse investments into other provinces and prevent from competing with each other.

“The private sector is very excited. We are expecting there will be a systematic investment by the private sector, which will accelerate the growth of electric cars,” said Sontirat.

As for the EV plan for passenger cars, the Electricity Generating Authority of Thailand (Egat) has collaborated with the National Science and Technology Development Agency (NSTDA) to make the EV Kit & Blueprint Project using Nissan cars Almera and Toyota Altis as prototype cars modified into EV cars. The blueprint will be publicised within this year.

The minister also plans to open a modified car garage. He said the opening of a car modification garage plan was delayed because the ministry still has to wait for the battery cost, which is the heart of the EV car, at lower than $150 per kilowatt-hour, to make it worth the investment and to create incentives for consumers to buy cars.

For buses, the collaboration between Egat and the NSTDA will be announced later. For electric motorcycles, 12 entrepreneurs are cooperating, both importing and assembling in the country, but they still have to wait for various issues, such as licences from the Department of Land Transport.

“What Egat does now is research and development to prepare the database until the demand is ready. It can be extended to commercial use immediately,” said Sontirat.

Energy Absolute Pcl executive committee chairman Somphote Ahunai said they were still waiting for clarity from the government. If it’s clear, then the company will review the EV charging stations business plan to speed it up.

More than 500 operations have been carried out, with 1,000 being completed within 2020, according to the original plan.

“If the government draws excess electricity backup to help reduce the electricity price, it will encourage private companies to invest more in EV charging stations. Vietnam and Indonesia are also focusing on promoting EV as well,” said Somphote.

Thailand plans to promote the use of EVs in four phases.

Phase I (2016-2017) – preparation of all sections; Phase II (2018-2020) – expand the results to public buses and prepare for personal electric cars.

Phase III (2021 onwards) – extend to promote personal electric cars; and Phase IV (2036 onwards) – electric vehicles to replace targeted 1.2 million oil vehicles.

THE NATION (THAILAND)/ASIA NEWS NETWORK

MOST VIEWED

  • Without shoes or a helmet, a young cyclist steals the show

    Pech Theara gripped the curved handlebars of his rusty old bike, planted his bare feet on its pedals and stormed as fast as he could towards the finish line. The odds were against him as the 13-year-old faced off against kids with nicer bikes at

  • Phnom Penh-Sihanoukville expressway on schedule

    The construction of the more than $1.9 billion Phnom Penh-Sihanoukville Expressway has not been delayed despite the Covid-19 pandemic, with more than 26 per cent of the project completed and expected to finish in about two years, according to Ministry of Public Works and Transport secretary of

  • Singapore group seeks $14M in damages from PPSP over ‘breach of contract’

    Singapore-based Asiatic Group (Holdings) Ltd is seeking a minimum of $14.4 million relief from Cambodia Securities Exchange (CSX)-listed Phnom Penh Special Economic Zone Plc (PPSP) for allegedly breaching a power plant joint venture (JV) agreement. Asiatic Group’s wholly-owned Colben System Pte Ltd and 95 per

  • Over 110 garment factories close

    A government official said on November 22 that at least 110 garment factories had closed in the first nine months of the year and left more than 55,000 workers without jobs – but union leaders worry those numbers could be much higher. Ministry of Labour and Vocational Training undersecretary

  • PM dispels lockdown rumours, gifts masks

    Prime Minister Hun Sen on November 12 denied rumours that he will lock down the country in response to increased Covid-19 fears, referring to them as propaganda aimed at destabilising the country. In a Facebook post, he said some people had spread rumours that the government

  • SilkAir adds flight to Phnom Penh schedule

    Silkair (Singapore) Pte Ltd is increasing its flight frequency between Phnom Penh and Singapore with a third weekly flight on Saturdays, according to Cambodia Airports’ Facebook page. The other flights offered are on Tuesdays and Sundays, with an estimated Phnom Penh arrival time at 5:35pm