Logo of Phnom Penh Post newspaper Phnom Penh Post - 2021 a crucial year for electricity decisions in Cambodia

2021 a crucial year for electricity decisions in Cambodia

Content image - Phnom Penh Post
A solar farm in Svay Rieng province. Photo Sunseap

2021 a crucial year for electricity decisions in Cambodia

I was asked recently, “What is holding back clean energy progress in Cambodia?” My answer was simple: electricity planning decisions. An electricity plan was made in the wake of the 2019 power shortages, but understandably that was made quickly and under pressure.

That plan will see 74 per cent of electricity supplied from fossil fuels by 2030, mostly from importing coal fired electricity from Laos or importing coal or gas to make electricity in Cambodia. The purchase price for the 2.4GW Laos coal project was stated in 2019 as $0.077/kWh – compare this with the competitive auction for a 60MW solar project at $0.0387/kWh led by the Electrite du Cambodge (EDC) and supported by the Asian Development Bank (ADB).

It’s only in the last two years that project developers in Cambodia have demonstrated that solar and wind can make electricity cheaper than burning coal, oil, gas and often hydro. This means new scenarios are required to compare costs and benefits with different share of this new solar and wind resource to ensure Cambodia is on the best economic and technical path.

Thankfully, the ADB is supporting the government to develop Power Development Master Plan out to 2040. It has been going slowly due to hesitation from the government to have scenarios comparing the 2019 plan with scenarios with higher levels of cheaper solar and wind power – and perhaps some the deals done in 2019 may need to be abandoned. But if Vietnam is planning to walk away from 17GW of coal projects on their books following the success of its domestic solar and wind industries, then it’s possible for Cambodia, too.

Fortunately, much of the technical data collection work has been done. Work completed last year by the Intelligent Energy Systems (IES), supported by the Australian government, concluded that Cambodia has 44GW of high potential solar, 6GW of wind, far higher than the 15GW Cambodia is projected to need by 2040. Back in 2017, expert electricity analysis funded by the ADB showed the Cambodian electricity grid can take 10-20 per cent capacity solar with no problem, up to 40 per cent with manageable limited impacts. Today, the grid is doing really well with eight per cent solar capacity, but that share will now decline as more coal projects come online. Cambodia now has excellent and commendable experience in integrating solar output into the grid – from 2016 when no solar was on the grid to over 0.23GW of solar by the end of last year.

So it is now possible to compare the Business as Usual 2019 plan with other scenarios with higher shares of solar and wind. Why should this be done? Because these sources are cheaper than coal, oil and gas. They are also produced within Cambodia, creating jobs, investment and contribute to the government’s aim of increasing energy independence. Only by comparing the technical and economic difference between the plan set after the 2019 power shortages with alternative plans can we know if Cambodia is on the right path. Certainly, Bloomberg New Energy Finance show global trends moving away from fossil fuels towards solar and wind, while Cambodia is rapidly heading in the opposite direction.

This is what Cambodia’s big investors – like Adidas, H&M, VF Corporation – have been asking the relevant ministers to consider. Forward looking companies have to meet their own global renewable commitments to their customers – and within a tight timeframe. The above mentioned garment companies make up more than 30 per cent of all Cambodia garment exports – more than $2 billion of exports. Factories producing for Adidas employ 80,000 Cambodians. These and many more companies operating in Cambodia are calling on the government to consider if the grid can avoid following the 2019 plan.

Equally important is the lost opportunity for more investment in Cambodia. The Laos 2.4GW of coal projects is around $3 billion of investment – inexplicitly not in Cambodia, but in Laos, even though the Cambodian government is underwriting those projects with a purchase agreement. If a competitive process was made for all that power to be produced in Cambodia, I wonder how much money could be saved on the electricity purchase price, and what jobs and investment could be made for the country?

The only way to know this is to model the scenarios and be willing to compare the costs, benefits and technical aspects of solar and wind. As a starting point, it should be easily possible to build on the existing hydro resources and model a scenario where half electricity is from renewable energy up to 2040.

This type of independent scenario analysis in China showed that increasing solar and wind generation (from three per cent now to 28 per cent and 11 per cent respectively) they could lower their electricity production costs from $0.0735/kWh to $0.065/kWh and reach half of generation from renewable energy by 2030 – well on the way towards supporting China to their net-zero target by 2060.

Cambodia is still at a crossroads and it’s not too late for Cambodia to alter its path. Those Laos coal projects haven’t closed finance, and there are some technical considerations such as the long transmission line from Laos to Phnom Penh, and even the availability of suitable coal deposits in Laos. There is still a chance to walk away from plans to have three quarters of Cambodia’s electricity depending on imports of coal, gas or electricity from neighbours. Cambodia can still consider the economic, social, environmental and energy independence benefits that could come from a more ambitious share of locally produced solar and wind power, and be a country demonstrating green energy leadership.

Bridget McIntosh is country director of EnergyLab in Cambodia – an organisation established to support the growth of the clean energy market in Cambodia (www.cleanenergycambodia.org)

MOST VIEWED

  • Ream base allegations must end, urges official

    A senior government official urges an end to the allegations and suspicions surrounding the development of Cambodia’s Ream Naval Base, now that Prime Minister Hun Manet has addressed the issue on the floor of the 78th UN General Assembly (UNGA 78). Jean-Francois Tain, a geopolitical

  • Cambodia set to celebrate Koh Ker UNESCO listing

    To celebrate the inscription of the Koh Ker archaeological site on UNESCO’s World Heritage List, the Ministry of Cults and Religion has appealed to pagodas and places of worship to celebrate the achievement by ringing bells, shaking rattles and banging gongs on September 20. Venerable

  • CP denied registration documents by ministry

    The Ministry of Interior will not reissue registration documents to the Candlelight Party (CP). Following a September 21 meeting between ministry secretary of state Bun Honn and CP representatives, the ministry cited the fact that there is no relevant law which would authorise it to do

  • PM to open new Siem Reap int’l airport December 1

    Prime Minister Hun Manet and Chinese leaders would jointly participate in the official opening of the new Chinese-invested Siem Reap-Angkor International Airport on December 1. The airport symbolises a new page in the history of Cambodian aviation, which will be able to welcome long-distance flights to

  • Cambodian diaspora laud Manet’s UN Assembly visit

    Members of the Cambodian diaspora are rallying in support of Prime Minister Hun Manet’s forthcoming visit to the 78th UN General Assembly (UNGA 78) in the US’ New York City this week. Their move is an apparent response to a recent call by self-exiled former

  • Minimum wage set at $204, after Sep 28 vote

    The minimum wage for factory workers in the garment, footwear and travel goods industries for 2024 has been decided at $204 per month, with the government contributing $2. Following several negotiation sessions, the tripartite talks reached an agreement during a September 28 vote, with 46 of 51 votes supporting the $202 figure.