Logo of Phnom Penh Post newspaper Phnom Penh Post - Kingdom wants more China energy investment

Kingdom wants more China energy investment

Content image - Phnom Penh Post
The Stung Atay Hydropower Project is a two-stage power plant with a total investment of $255 million. Pha Lina

Kingdom wants more China energy investment

CHINA DAILY/ANN: At the China-ASEAN Expo this September in Nanning, Prime Minister Hun Sen of Cambodia, the event’s “Country of Honour”, regaled the participants with tales of how it was the 11th time he had led a delegation to the expo.

His commitment soon paid off. In four days, his delegation had swept up deals worth $80 million with China.

The two countries had just celebrated the 60th anniversary of diplomatic ties in July, and bilateral trade had swollen to $5.8 billion last year, an all-time high. As its biggest trade partner and investor, China is an important ally in Cambodia’s economic revitalisation. Yet the Kingdom’s dire situation of infrastructure development remains a big hurdle.

It’s no wonder that Hun Sen took time from his tight schedule to hold an investment forum with executives from Chinese enterprises involved in Cambodia’s infrastructure construction under the China-proposed Belt and Road Initiative (BRI).

Among them was Chen Feihu, president of China Datang Corp, a state-owned power generator and a $25 billion Fortune Global 500 company.

In dire need

Back in 2009, when Datang set out to build a hydropower dam and power grid in southwest Cambodia’s tropical jungles, the challenges the engineers faced included not only the road-less hilly terrain and the debilitating weather, but also the wild beasts and gnawing boredom from weeks of isolation deep inside the forests.

“To do construction work in a place like Cambodia, as we all know, is very difficult,” said Qiu Huibin, a Datang manger in charge of the local projects.

Cambodia was then in dire need of an increase in its own power supply and expansion of access to the power grid. A remedy was long overdue as the Kingdom was heavily reliant on pricey electricity imports from neighbouring countries like Thailand, Vietnam and Laos. The imports rate reached an alarming 64 per cent in 2011, nearly two-thirds of its electricity consumption. Even worse, large swathes of its countryside remained off-grid and dirty diesel generators were their only resort.

“The four provinces along the route from Phnom Penh to Battambang are mostly economically-deprived, and families in those regions didn’t have access to power,” said Tea Kong, the Cambodian minister-counsellor to China, in an interview with China Daily.

The projects’ official launch in early 2014 couldn’t have been timelier. The Cambodian government had just unveiled a new five-year development plan, the Rectangular Strategy Phase III, vowing to “reclaim full ownership of the country’s destiny”.

At the launch ceremony, Hun Sen lauded Datang for “helping power the Cambodian battery”, honouring six of its employees with the prestigious medal of “Friendly Cooperation”.

The Stung Atay Hydropower Project is a two-stage power plant with a total investment of $255 million.

The first involves the installation on the dam toe of two sets of 10MW hydro turbines and generator units, while the second stage focuses on the lower dam’s powerhouse, with four more units and another 100MW capacity. To build such a concrete-and-steel mammoth deep in the rainforests, only 22km away from Cambodia’s second-highest peak, was an uphill task.

The Phnom Penh-Battambang 230kV Power Transmission Project was no less arduous as the power grid winds almost 300km across the mountain ranges, connecting the capital city Phnom Penh with the four provinces of Kandal, Kampong Chhnang, Pursat and Battambang, bringing light to local residents and driving economic development along its entire route.

Since both projects operated under so-called build-operate-transfer (BOT) contracts, their BOT framework met Cambodia’s pressing need for capital and technology at an early stage of development, helping cultivate 132 local power technology and management personnel and create more than 10,000 jobs.

As of May, the Stung Atay power plant had supplied Cambodia with nearly 1.2 billion kWh of power and nearly one third of the country’s power transmission last year was carried by the Phnom Penh-Battambang power grid.

The country’s electricity imports rate was reduced to 22 per cent in 2016, and is still declining.

Infrastructure cooperation between China and Cambodia is riding on a high tide as the BRI enters its fifth year. Cambodia’s biggest hydropower dam, the Lower Sesan II, which was built by China Huaneng Group, began operations last November.

Construction of a new airport in Siem Reap began this spring while China Road and Bridge Corp is ready to start a highway project from Phnom Penh to the Sihanoukville Special Economic Zone as soon as this month.

MOST VIEWED

  • Would you like fries with that? US burger chain makes Phnom Penh debut

    California-based The Habit Burger Grill restaurant chain is all set to serve up a delicious array of charbroiled burgers and sides at its newest international location in the centre of Phnom Penh. The Habit is “renowned for its award-winning Charburgers grilled over an open flame,

  • Angkor provides ‘valuable’ water storage

    The Apsara National Authority (ANA) has stored millions of cubic metres of water at reservoirs in the Angkor area after Cambodia experienced a series of rainstorms over the last few days. The storing of the water, besides serving temple conservation, will also be used to

  • Banteay Meanchey floods kill one more as death toll reaches 15

    As floodwaters start to recede in Pursat, Battambang and Pailin provinces and Phnom Penh, Banteay Meanchey continues to bear the brunt as one more person was killed on Monday, bringing the total number of flood-related deaths to 15 in the province this month. Banteay Meanchey provincial

  • Floods prompt evacuations in Kampong Speu

    Rain-induced floods and water flowing from Kampong Speu province have submerged the houses of 1,527 families living close to the Prek Thnot River in Spean Thma, Tien, Kong Noy and Roluos communes in Phnom Penh’s Dangkor district, according to data from local authorities. Spean Thma

  • Serving coffee with a side of robots

    The eye-catching glass building surrounded by greenery at the intersection of Streets 371 and 2002 in Phnom Penh’s Sen Sok district is more than just another coffee shop where you can while away a few hours. UrHobby House cafe is filled with robots and characters from

  • Banteay Meanchey flood victims receive aid

    Prime Minister Hun Sen on Wednesday provided aid to more than 10,000 families affected by flooding in Banteay Meanchey province’s Mongkol Borei district and offered his condolences to the 18 victims who drowned in the province over the past week. He said flooding had occured in