Logo of Phnom Penh Post newspaper Phnom Penh Post - Vietnam won’t add wind, solar power in 2022

Vietnam won’t add wind, solar power in 2022

Content image - Phnom Penh Post
The use of renewable energy (RE) sources in Vietnam is set to face many difficulties in 2022 due to power grid limitations. VNEXPRESS.NET

Vietnam won’t add wind, solar power in 2022

Vietnam's Ministry of Industry and Trade will not add any more wind and solar power into this year’s plan, due to a lack of input facilities to transfer them to the national grid.

At the 2021 review meeting of the National Load Dispatch Centre on January 10, its deputy director Nguyen Quoc Trung said the total electricity produced and imported including rooftop solar power output was expected to reach 275.5 billion kWh this year, up 7.9 per cent compared to 2021.

Trung said that total hydropower output was expected to be 82.5 billion kWh, 3.8 billion kWh higher than in 2021.

Traditional power sources expected to come into operation in 2022 were 3,407MW, including large thermal power plants with a capacity of 600MW each plant, such as the Nghi Son 2 and Song Hau 1, with no more wind power, farm solar power and rooftop solar power to the grid this year.

Trung also said the southeast gas source would reach 13.5-14.5 million cubic metres per day, while the southwest gas sources would reach from 3.9-4.5 million cubic metres in the year.

Buying electricity from China with an output of about 380 million kWh in May and June was also expected.

For the north of Vietnam, Trung said the peak load was expected to grow by 9.5-13 per cent, or increase by 2,497-2,870MW in the year.

Though the north will have many potential risks of shortages during peak capacity, especially during the peak hot months from May to July, the National Load Dispatch Centre has proposed asked to adjust the repair schedule, changing the wiring in Nghi Son when necessary so that the Nghi Son 2 plant could supply the region when necessary, together with calculating the purchase of Chinese electricity under the direction of Vietnam Electricity (EVN).

“Currently, low cost gas fields are decreasing while high cost gas fields were put into operation with the policy that BOT [build-operate-transfer] gas-fired power plants continue to be used, leading to the higher cost of new gas fields, affecting the electricity cost of the whole system,” Trung said.

Even after energising all approved new projects to ensure power supply to important load centres such as Hanoi and Ho Chi Minh City as well as to release renewable energy (RE), most of the 500kV transformers were at full load.

“The using of RE sources in 2022 continues to face many difficulties, because the power grid has suffered with the amount of RE sources that have been put into operation in recent years,” Trung said.

The challenges were reported in the provinces of Binh Dinh, Khanh Hoa, Phu Yen, Ninh Thuan, Binh Thuan, Ca Mau, Bac Lieu, Dak Lak, Dak Nong, Kon Tum and Gia Lai – the latter four of which border Cambodia.

In addition, with the increasing rate of RE sources put into operation, the problem of stabilising the power system in real time was still a big challenge, he added.

Last year, the total new power source put into operation was 7,433MW, bringing the total installed capacity of the national power system to 78,682MW including 75 wind power plants with a total capacity of about 3,600MW.

By the end of 2021, the total number of national dispatching plants was 337, an increase of 73 plants compared to 2020.

Currently, there are 104 plants directly participating in the power market with a total installed capacity of 27,990MW, accounting for 36.8 per cent of the total installed capacity of power plants. During the year, four new factories entered the market with a total capacity of 372MW.

In addition, the national dispatcher energised, tested and accepted many important transmission lines and transformers projects on the 500kV power grid such as energising eight new transformers with a total capacity of 4,387MVA, increasing the capacity of five transformers with a total capacity of 3,900MW, and 14 newly energised 500kV lines with a total length of 2,022km.

At the same time, the industry has built 203 new 220kV-110kV transformers with a total capacity of 13,016MVA, and 236 new sections of 220kV-110kV transmission lines with a total length of 3,450km.

VIET NAM NEWS/ASIA NEWS NETWORK

MOST VIEWED

  • Siem Reap drain canal now ‘mangrove’ promenade

    A more than half a kilometre long stretch of canal in Siem Reap has been covered and turned into a promenade to attract visitors, said Ly Rasmey, secretary of state at the Ministry of Land Management, Urban Planning and Construction, on September 16. The new pedestrianised

  • Angkor wildlife, aquarium park still to open October

    The Angkor Wildlife and Aquarium complex about 30km southeast of Siem Reap town with initial total investment of more than $70 million is reportedly still on track for an end-October opening. The park is located on a 100ha plot along National Road 6 in Kbon village, Khchas

  • Final verdicts for Khmer Rouge leaders ‘vital’ for next generation

    Nearly a decade after the commencement of Case 002/02 against Khieu Samphan back in 2014, the Extraordinary Chambers in the Courts of Cambodia (ECCC) is now set to deliver its final verdict for the former Khmer Rouge head of state. The Supreme Court Chamber of the ECCC,

  • Typhoon Noru brings flash floods – 16 dead

    An official warned that that the 16th typhoon of the season, Noru, had brought heavy rains to areas the Mekong River and flooded thousands of homes in the provinces bordering Thailand. As of September 27, the death toll from the flooding had risen to 16. National Committee

  • Defence minister reaffirms Kingdom’s staunch support for One-China policy

    Minister of National Defence General Tea Banh has reaffirmed Cambodia’s unwavering support for the One-China policy. Tea Banh was speaking at the September 20 ceremonial handover of 117 vehicles and other military equipment donated by China’s defence ministry, held at Phnom Chumreay International Military Training

  • Deaths due to ‘lifestyle’ diseases rise in Kingdom

    The Ministry of Health has called on people to pay closer attention to their health to protect themselves from non-communicable diseases (NCDs) which it said have caused high rates of deaths in the country. Ministry secretary of state York Sambath made the call at a