Siem Reap airport to be 67% done by end of 2021

Content image - Phnom Penh Post
An artist’s impression of the new Siem Reap Angkor International Airport. SASAC.GOV.CN

Siem Reap airport to be 67% done by end of 2021

Construction on the new nearly-$900 million airport project in Siem Reap province will be 67 per cent complete by the end of next year, according to Angkor International Airport Investment (Cambodia) Co Ltd (AIAI) chairman Lu Wei.

Lu made the remark during a second visit by Mao Havannall, the minister in charge of the State Secretariat of Civil Aviation (SSCA), to inspect the project’s progress on December 23.

While the spread of Covid-19 has resulted in unprecedented disruptions, Lu said construction is more than 30 per cent complete since the project broke ground on March 15.

He said the basement had been 100 per cent completed, and the ground and first floors of the passenger terminal building had been “100 per cent concreted”, while the second floor had been “25 per cent concreted”.

“On October 15, we started construction of the aircraft fuel depot, and on November 1, we started work in the flight area. So far, we have cleared 80 per cent of the land of the construction site,” he said.

Lu also confirmed that the flyover construction team started work on December 23.

In addition to the thoroughfare linking the project to National Road 6, the company has built an 8km road connecting National Road 64 to the passenger terminal, which will be paved soon, he said.

Fence-building and related works are underway for a 16.5km section of road that connects national roads 6 and 64, he said.

He said the company is currently in talks with Electricite du Cambodge (EdC), with plans in the pipeline to sign a memorandum of understanding with the state-run energy supplier next year for a new electrical substation and a 230kW power transmission line connecting to the project.

“According to our plan, by December 31, 2021, all construction work will be 67 per cent completed. Of this, 77 per cent of the passenger terminal project will be completed, 45 per cent of the flyover will be completed and 50 per cent of the other infrastructure work will be completed,” Lu said.

Havannall lauded the company’s efforts, despite the disruption fuelled by the Covid-19 pandemic, which has hampered construction projects nationwide.

“We appreciate the company and colleagues for their hard work. Without their efforts, we couldn’t have reached today’s achievements . . . As Mr chairman Lu Wei said, he overcame the circumstances in which we were living in – Covid-19.

“Through Mr Lu Wei’s report, I can ascertain that we have more than 30 per cent of the overall project done . . . my conclusion is that this is in line with Mr Lu Wei’s claim that by the end of 2021, 67 per cent of the construction will have been completed,” he said.

Addressing Lu, Havannall added: “I hope that in 2021 you’ll have 67 per cent finished and that in 2022, we won’t have much work left . . . In 2022, we’ll complete our new Siem Reap airport.”

The new airport is being built on a 750ha plot in Ta Yek commune, Sotr Nikum district east of Siem Reap town at a cost of $880 million. The project is being built in three phases.

AIAI will invest $500 million for the first and second phases, which will allow medium-sized and ranged passenger aircraft like the Boeing 737 and Airbus A320 to land. Another $300 million will be allocated for the third phase.

In October 2017, the government reached an agreement with Chinese state-run Yunnan Investment Holdings Ltd to build the new airport to serve Siem Reap.

The agreement gave the firm and its construction and airport management subsidiaries an exclusive 55-year build, operate, transfer (BOT) concession on the new airport, replacing the current exclusive agreement with Cambodia Airports, a company majority-owned by France’s VINCI Group, which was set to expire in 2040.

The airport will be able to handle 10 million passengers in 2030 and 20 million by 2050.

MOST VIEWED

  • South Korea’s first lady brings hope to ill boy

    South Korea’s first lady Kim Keon-hee – wife of current president of the Republic of Korea, Yoon Suk Yeol – met with a 14-year-boy with congenital heart disease during her trip to the Kingdom for the ASEAN Summit. After their meeting it was announced that the

  • Hun Sen gets Covid, shuns G20, APEC summits

    Prime Minister Hun Sen said he has tested positive for Covid-19 in Indonesia, where he is slated to attend the G20 summit in his capacity of the ASEAN chair. In a social media post addressing the Cambodian public, he said: “Before leaving Cambodia, I always

  • Moody’s sets outlook rating to ‘negative’ for Cambodia

    US global rating agency Moody’s Investors Service Inc on November 15 announced that it downgraded Cambodia’s outlook from “stable” to “negative” and maintained its B2 local and foreign currency issuer ratings. “The negative outlook reflects a deteriorating external position as illustrated by the severe

  • Hun Sen’s Covid infection caused by ‘weakened antibody’ after summit

    Prime Minister Hun Sen said exhaustion from heavy workload before and during the recent ASEAN Summit may have led to him contracting Covid-19 due to his weakened immune system, while rejecting speculations that the infection was caused by leaders of some countries who did not

  • Korean first lady paves way for ill boy’s surgery

    A 14-year-old boy with congenital heart disease who was lucky enough to meet with South Korean first lady Kim Keon-hee may get the chance of a lifetime and receive surgery and treatment at Asan Medical Center in Seoul, South Korea. After seeing his plight, many

  • Kingdom’s rice crowned world’s No1

    Cambodia’s Phka Rumduol jasmine variety has been crowned the World’s Best Rice for the fifth time at the TRT (The Rice Trader) World Rice Conference in Phuket, Thailand on November 17, according to leaders of the Kingdom’s apex rice industry body. Phka Rumduol